Job Centre, Dortmund, Germany
Competition: 1988 - 1st Prize
Construction period: 1992 - 1995
Design: Eckhard Gerber
Project director/Project manager: Georg Kolendowicz
Project team: Jens Haake, Chrstoph Nolte, Hans C. Bittner,Volker Brockmeier, Björn Corneliussen, Jens Haake, Claudia Müller, Michael Plasa, Raimund Stüssel, Uwe Goldstein et al.
Client: Bundesanstalt für Arbeit Nürnberg vetr.durch das OBF Münster vert. durch das Staatliche Bauamt Dortmund
Gross area: 38.700 m²
Volume: ca.130.000 m³
Two building wings along the streets form an angle, which leaves a great part of the site as a public green, protected from the adjacent streets. The tense relation between city and land-scape as a basic design feature is also reflected in the façades, which are closed and clad with stones towards the streets but are filigree and transparent towards the park.